Following demolition of the site infrastructure, GEMEC undertook soil remediation works on the 4,700 square metre site, excavating 9,100 cubic metres of contaminated soil.
About half of the soil was successfully bioremediated on site. The remainder was transported to our solid waste facility north of Perth, where it was also successfully bioremediated.
Stages of the project




More projects

Former bitumen manufacturing plant
4,300 m³ of contaminated soil excavated and bioremediated on site, with auditor sign-off achieved.

40,000 L crude oil soil remediation
Crude-oil-contaminated soil bioremediated to below WA commercial/industrial guideline levels.